News

ABB Wins $30 Million Solar Power Plant Order in Spain

15.03.2010 -

ABB has won a $30 million order from GA Solar, part of the Gestamp Corporation, to deliver a 13 megawatt (MW) photovoltaic (PV) power plant in northern Spain.

Once connected to the grid, the plant will supply up to 22.6 gigawatt hours (GWh) of electric power a year, avoiding the generation of over 11,500 tons of CO2 emissions, equivalent to the annual emission of over 4,800 European cars.

ABB will be responsible for the design, engineering, erection, civil works and commissioning of the plant, which is scheduled for completion within the year thanks to ABB's modular eBOP (electrical balance of plant) concept. By pre-assembling individual components of the plant's electrical systems in modules and testing them prior to delivery, on-site installation and commissioning is fast and simple, reducing costs and project risks.

ABB's 1 MW PV power plant modules generate around 15% more energy than alternative units in this range. ABB will supply all the electrical equipment required to connect the plant to the grid, including medium- and low-voltage switchgear, transformers and a medium-voltage substation. ABB will also install patented control and automation technologies including a tracker system to enable the plant's solar panels to follow the sun's movement across the sky and maximize generating capacity.

Kontakt

ABB Automation Products GmbH

Wallstadter Straße 59
68526 Ladenburg
Deutschland

+49 6023 71 0
+49 6023 71 2559